A robot can appear still while hazardous energy remains in the wider cell. When maintenance involves several teams, a handover that says only “machine stopped” leaves important questions unanswered: which equipment is covered, who controls the work area, and who has authority to release it? This article helps service coordinators organize the information around a maintenance job. It is not a procedure for isolating a specific machine and does not authorize anyone to work on energized equipment.
Describe the task and identify the robot, controller, end effector and associated equipment that could affect it. Conveyors, fixtures, compressed air, gravity-loaded parts and other sources can change the scope of a maintenance job. Ask the site owner and qualified service personnel to review the actual installation and manufacturer instructions; a list copied from a different workcell may omit an important connection.
Record who requested the work, the planned location, the affected production area and the site contact. If the planned work changes after inspection, stop and have the responsible people reassess the scope before continuing. The purpose of the record is to coordinate a reviewed process, not to let a remote coordinator declare the installation safe.
A normal stop command, a control-screen indication or an emergency-stop button should not be assumed to provide the energy isolation required for servicing. The UK Health and Safety Executive's work equipment maintenance guidance discusses isolation, stored energy and coordination with contractors. Other jurisdictions and equipment can have different legal and technical requirements; consult the rules and procedures that apply at the site.
The responsible site team should identify energy sources and approved isolation points using the actual equipment documentation and risk assessment. Mechanical movement, pneumatic pressure, electrical energy and other hazards must be evaluated by qualified people. A record of a screen status or a verbal assurance alone is not equivalent to verification. The service organization should not invent an isolation method when the manufacturer information is missing.
When a contractor joins the site team, exchange relevant procedures and identify who coordinates the job, who is authorized to perform each safety task, and how affected staff will be informed. Specify the period during which the work area is controlled and who can approve a change in scope. A shift change should include an explicit transfer of responsibility; a person arriving later needs to know what has already been checked and what remains unresolved.
The UK Health and Safety Executive's electrical safety questions and answers discusses different energy sources, manufacturer instructions and local rules. Use it to understand why the work scope needs review, while relying on local site rules and competent personnel for the actual work.
A service ticket can list the reported symptom, planned inspection, equipment identifiers and the person responsible for coordinating access. The site's approved energy-control record should document the procedures and verification required for the job. Keep both linked, but do not let an administrative ticket substitute for the controlled procedure. If a safety record is unavailable or incomplete, record the hold and contact the site owner rather than writing “safe” on behalf of another team.
For a hypothetical example, a technician is asked to inspect a gripper fault and learns that the gripper has a separate pneumatic supply. The correct administrative response is to notify the site coordinator that the original work scope may be incomplete and wait for an authorized reassessment. The coordinator's note should capture the discovery and the decision; it should not instruct an unqualified person to manipulate a valve.
In the job file, retain the revision or identifier of the approved procedure rather than copying a partial set of steps into an email. The site can then confirm that the people doing the work have access to the current version. List each contractor organization involved, the time of the coordination briefing and the contact for an unexpected change. If the work is deferred to another day, check that the original authorization and scope are still valid before rescheduling; conditions in the cell may have changed in the meantime. These administrative controls support the people responsible for the task, but do not establish that isolation has been performed.
Before the job starts, agree who will inspect the work area, account for personnel and tools, manage removal of controls and authorize return to service under the site's procedures. Record any unresolved defects and restrictions for the next shift. If a repair was not approved or a replacement part is missing, distinguish the completed inspection from permission to operate. A maintenance note should identify the decision maker and the scope of any follow-up, not imply that normal production has resumed merely because the technician left.
Read our guide to separating inspection from repair approval and explore the robot service information collection for related handover topics. Site-specific safety procedures and qualified personnel remain essential throughout the work.